✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | |||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
# |
dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
||||||||||
1 | 6/2017 | D1 | 7,9 km | 4 | 2 237 m | 434 mil. € | 19 072 - 21 988 | 1 935 - 2 218 | 1 | 2 | 7/2021 (0,0) | |||||
2 | 12/2017 | D1 | 2,6 km | 4 | 0 m | 39 mil. € | 14 624 | 1 378 | 1 | 1 | 0,0 | 2021 (+2,2) | ||||
3 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 0 m | 133 mil. € | 5 814 - 7 518 | 349 - 902 | 4 | 3 | 6,0 | 5/2033 (+6,1) | |||
4 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 0 m | 124 mil. € | 3 769 - 3 897 | 1 289 - 1 580 | 3 | 3 | 6,0 | 5/2033 (+6,1) | |||
5 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 0 m | 101 mil. € | 3 782 - 6 302 | 1 492 - 1 737 | 4 | 3 | 6,0 | 5/2033 (+6,1) | |||
6 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 0 m | 182 mil. € | 7 234 | 632 | 4 | 3 | 8,0 | 7/2033 (+4,3) | |||
7 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 0 m | 222 mil. € | 2 561 - 5 054 | 427 - 551 | 4 | 3 | 8,0 | 7/2033 (+4,3) | |||
7 úsekov |
54,4 km |
2 - 4 |
2 237 m |
1 235 mil. € |
2 561 - 21 988 | 3,0 |
2,6 |
7/2021 - 7/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku