dátum |
plánovaný
|
odhad NDS
|
1 - optimálne,
5 - neprimerané | |||||||||
1 | 24. | 12/2025 | ![]() | R2 | 6,1 km | 4 | 178 m | 143 mil. € | 4 | 48. | |||
2 | 20. - 23. | 10/2025 | ![]() | R2 | 2,7 km | 4 | 61 m | 59 mil. € | 4 | 23. | |||
3 | 19. | 6/2025 | ![]() | R4 | 8,2 km | 2 | 34 m | 94 mil. € | 3 | 36. | |||
4 | 20. - 23. | 10/2025 | ![]() | R3 | 8,3 km | 2 | 192 m | 199 mil. € | 3 | 17. | |||
5 | 7/2019 | ![]() | R4 | 4,3 km | 4 | 337 m | 179 mil. € | 3 | |||||
6 | 20. - 23. | 10/2025 | ![]() | R3 | 4,9 km | 2 | 0 m | 77 mil. € | 2 | 16. | |||
7 | 20. - 23. | 10/2025 | ![]() | R2 | 16,0 km | 4 | 496 m | 277 mil. € | 2 | 23. | |||
8 | 8/2019 | ![]() | R2 | 13,5 km | 4 | 142 mil. € | 2 | ||||||
9 | 18. | 4/2025 | ![]() | D1 | 1,1 km | 2 | 126 m | 12 mil. € | 1 | ||||
9 úsekov |
65,0 km |
2 - 4 |
1 424 m |
1 181 mil. € |
2,7 |
16. - 48. |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku