dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
14 úsekov |
109,0 km |
2 - 4 |
2 550 m |
1 943 mil. € |
2,8 |
2,8 |
18 - 54 |
|||||||
1 | 24. | 12/2025 | R2 | 6,1 km | 4 | 178 m | 143 mil. € | 3 | 4 | 24 | ||||
2 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 61 m | 59 mil. € | 3 | 4 | 23 | ||||
3 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 86 m | 133 mil. € | 4 | 3 | 51 | ||||
4 | 19. | 6/2025 | R4 | 8,2 km | 2 | 34 m | 94 mil. € | 3 | 3 | 19 | ||||
5 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 440 m | 182 mil. € | 4 | 3 | 53 | ||||
6 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | 192 m | 199 mil. € | 2 | 3 | 21 | ||||
7 | 7/2019 | R4 | 4,3 km | 4 | 337 m | 179 mil. € | 1 | 3 | ||||||
8 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 137 m | 124 mil. € | 3 | 3 | 50 | ||||
9 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 199 m | 101 mil. € | 4 | 3 | 52 | ||||
10 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 265 m | 222 mil. € | 4 | 3 | 54 | ||||
11 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 0 m | 77 mil. € | 2 | 2 | 20 | ||||
12 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 496 m | 277 mil. € | 2 | 2 | 22 | ||||
13 | 8/2019 | R2 | 13,5 km | 4 | 142 mil. € | 2 | 2 | |||||||
14 | 18. | 4/2025 | D1 | 1,1 km | 2 | 126 m | 12 mil. € | 2 | 1 | 18 | ||||
14 úsekov |
109,0 km |
2 - 4 |
2 550 m |
1 943 mil. € |
2,8 |
2,8 |
18 - 54 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku