dátum |
plánovaný
|
odhad NDS
|
<3,5 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
prebratie
| |||||||||||
1 | 7/2019 | R4 | 4,3 km | 4 | R4 stred | R 24,5/100 | 179 mil. € | 15 837 - 18 098 | 917 - 967 | 1 | 3 | 5/2015 | ||||||
2 | 8/2019 | R2 | 13,5 km | 4 | R2 stred | R 24,5/100 | 142 mil. € | 9 007 - 9 998 | 831 - 943 | 2 | 2 | 7/2014 | ||||||
3 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | R1 BB - RK | R 24,5/80 | 785 mil. € | 8 140 - 13 204 | 575 - 1 052 | 3 | 3 | 8/2015 | |||||
4 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | R2 východ | R 24,5/120, plánované v 1/2-profile | 73 mil. € | 5 587 | 488 | 5 | 4 | 4/2015 | |||||
5 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | D1 západ | D 33,5/120 | 321 mil. € | 42 774 - 54 519 | . . . | 2 765 - 3 271 | 3 | 2 | |||||
6 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | R2 západ | R 24,5/120(100), plánované v 1/2-profile | 112 mil. € | 8 634 - 11 116 | 635 - 690 | 2 | 4 | 9/2014 | |||||
7 | 41. | 9/2028 | R2 | 11,5 km | 2 | R2 západ | R 24,5/120, plánované v 1/2-profile | 235 mil. € | 7 793 | 655 | 2 | 4 | 9/2014 | |||||
8 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | R4 sever | R 24,5/100, plánované v 1/2-profile | 129 mil. € | 2 552 - 2 737 | 177 - 189 | 4 | 3 | 12/2014 | |||||
9 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | R3 juh | R 24,5/120, plánované v 1/2-profile | 63 mil. € | 9 492 - 10 279 | 332 - 531 | 3 | 2 | 5/2015 | |||||
9 úsekov |
94,4 km |
2 - 6 |
2 038 mil. € |
2 552 - 54 519 | 2,8 |
3,0 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku