dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
prebratie
| |||||||||
12 úsekov |
119,9 km |
2 - 4 |
3 082 mil. € |
3,0 |
3,3 |
||||||||||
1 | 3/2020 | R2 | 9,1 km | 4 | R2 stred | 267 mil. € | 1 840 | 3 | 4 | 7/2014 | |||||
2 | 7. | 2/2024 | D1 | 13,5 km | 4 | D1 sever | 1 235 mil. € | 6 458 | 1 | 1 | |||||
3 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | R2 stred | 105 mil. € | 2 002 | 2 | 2 | 6/2014 | ||||
4 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | R7 západ | 191 mil. € | 3 150 | 4 | 5 | 11/2014 | ||||
5 | 10. | 4/2024 | D1 | 3,8 km | 2 | D1 sever | 57 mil. € | 3 | 5 | ||||||
6 | 11. | 6/2024 | R1 | 2,7 km | 4 | R1 BB - RK | 155 mil. € | 1 230 | 4 | 3 | 8/2015 | ||||
7 | 12. | 7/2024 | R3 | 6,5 km | 2 | R3 juh | 70 mil. € | 1 489 | 2 | 2 | 5/2015 | ||||
8 | 13. | 8/2024 | R2 | 8,3 km | 2 | R2 stred | 169 mil. € | 2 147 | 2 | 2 | 6/2014 | ||||
9 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | R7 západ | 227 mil. € | 1 508 | 4 | 4 | 11/2014 | ||||
10 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | R7 západ | 172 mil. € | 965 | 4 | 4 | 11/2014 | ||||
11 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | R7 západ | 161 mil. € | 2 880 | 4 | 5 | 11/2014 | ||||
12 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | R2 východ | 272 mil. € | 3 | 2 | 4/2015 | |||||
12 úsekov |
119,9 km |
2 - 4 |
3 082 mil. € |
3,0 |
3,3 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku