dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
1 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | Trenčianske Mitice | 277 mil. € | 15,4 km | 2 | 2 | 12/1998 | |||
2 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | Podbiel | 199 mil. € | 10,0 km | 2 | 3 | 7/1993 | |||
3 | 19. | 6/2025 | R4 | 8,2 km | 2 | Svidník sever | 94 mil. € | 7,9 km | 3 | 3 | 1/2000 | |||
4 | 24. | 12/2025 | R2 | 6,1 km | 4 | Trenčín juh, Trenčianska Turná | 143 mil. € | 5,7 km | 3 | 4 | 12/1998 | |||
5 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | Dlhá nad Oravou | 77 mil. € | 5,1 km | 2 | 2 | 7/1993 | |||
6 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 59 mil. € | 3,2 km | 3 | 4 | 12/1998 | ||||
7 | 3. | 3/2022 | D1 | 3,5 km | 8 | Ivanka sever | 149 mil. € | 1 | 1 | 11/2008 | ||||
8 | 4. | 9/2022 | R4 | 10,2 km | 4 | Kapušany | 299 mil. € | 1 | 3 | 5/2002 | ||||
9 | 18. | 4/2025 | D1 | 1,1 km | 2 | 12 mil. € | 2 | 1 | 7/2002 | |||||
60,9 km |
2 - 8 |
1 308 mil. € |
47,3 km |
2,1 |
2,6 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku