plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||
13 úsekov |
118,2 km |
2 - 8 |
2 121 mil. € |
2 561 - 62 652 | 3,7 |
3,4 |
9/2025 - 9/2033 |
||||||
1 | D1 | 3,5 km | 8 | 149 mil. € | 62 652 | . . . | 1 | 1 | 9/2025 (+4,6) | ||||
2 | R4 | 10,2 km | 4 | 299 mil. € | 22 341 - 30 731 | 1 | 3 | 1/2027 (+4,8) | |||||
3 | R2 | 18,0 km | 2 | 176 mil. € | 5 189 - 6 389 | 5 | 5 | 2/2032 (+4,9) | |||||
4 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 2/2033 (+4,5) | ||||||
5 | D1 | 7,3 km | 4 | 321 mil. € | 10 359 | 3 | 3 | 9/2033 (+5,8) | |||||
6 | R2 | 14,0 km | 2 | 117 mil. € | 5 809 - 8 826 | 5 | 4 | 7/2032 (+5,3) | |||||
7 | R2 | 9,8 km | 2 | 93 mil. € | 6 452 - 10 032 | 5 | 5 | 9/2032 (+5,6) | |||||
8 | R3 | 7,9 km | 2 | 71 mil. € | 5 441 - 8 427 | 4 | 3 | 9/2032 (+4,1) | |||||
9 | R4 | 8,0 km | 2 | 133 mil. € | 5 814 - 7 518 | 4 | 3 | 5/2033 (+6,1) | |||||
10 | R4 | 7,5 km | 2 | 124 mil. € | 3 769 - 3 897 | 3 | 3 | 5/2033 (+6,1) | |||||
11 | R4 | 6,0 km | 2 | 101 mil. € | 3 782 - 6 302 | 4 | 3 | 5/2033 (+6,1) | |||||
12 | R6 | 11,2 km | 2 | 182 mil. € | 7 234 | 4 | 3 | 7/2033 (+4,3) | |||||
13 | R6 | 11,3 km | 2 | 222 mil. € | 2 561 - 5 054 | 4 | 3 | 7/2033 (+4,3) | |||||
13 úsekov |
118,2 km |
2 - 8 |
2 121 mil. € |
2 561 - 62 652 | 3,7 |
3,4 |
9/2025 - 9/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku