dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||||
11 úsekov |
111,2 km |
2 - 4 |
8 603 m |
2 778 mil. € |
6 412 - 50 895 | 2,6 |
3,2 |
||||||||||
1 | 5. | 4/2023 | R1 | 8,1 km | 4 | 1 018 m | 173 mil. € | 38 235 | 12 387 - 17 316 | 2 | 3 | 9,0 | |||||
2 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 20 978 | 3 | 4 | 4,0 | |||||||
3 | 6. | 7/2023 | R2 | 6,8 km | 4 | 1 169 m | 171 mil. € | 12 495 - 26 580 | 11 764 - 50 895 | 3 | 3 | 9,0 | |||||
4 | 25. | 1/2026 | D3 | 10,8 km | 4 | 804 m | 309 mil. € | 28 654 | 14 176 - 14 186 | 2 | 4 | 6,0 | |||||
5 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | 578 m | 105 mil. € | 11 489 | 14 625 | 2 | 2 | 5,0 | |||||
6 | 26. | 4/2026 | R2 | 20,7 km | 2 | 886 m | 211 mil. € | po Lučenec 9 371, ďalej 8 954 | 6 969 - 10 726 | 4 | 4 | 5,0 | |||||
7 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | 1 015 m | 224 mil. € | 15 407 | 10 140 - 11 010 | 3 | 5 | 5,0 | |||||
8 | 31. | 11/2026 | D3 | 4,0 km | 4 | 179 mil. € | 26 769 | 15 053 | 1 | 2 | 7,0 | ||||||
9 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | 253 m | 125 mil. € | po R. Sobotu 7 978, ďalej 8 783 | 6 412 - 8 112 | 4 | 4 | 5,0 | |||||
10 | 30. | 10/2026 | R1 | 4,6 km | 4 | 1 757 m | 100 mil. € | 14 868 | 11 611 | 4 | 3 | 3,0 | |||||
11 | 27. | 5/2026 | D3 | 11,2 km | 4 | 1 124 m | 410 mil. € | 38 080 | 13 886 - 21 743 | 1 | 1 | 7,0 | |||||
11 úsekov |
111,2 km |
2 - 4 |
8 603 m |
2 778 mil. € |
6 412 - 50 895 | 2,6 |
3,2 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku