dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka | ||||||||||
1 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | Senec | 234 mil. € | 62 652 | . . . | 2 | ||||
2 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | Dlhá nad Oravou | 77 mil. € | 2 | ||||||
3 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | Kuková | 1 | 116 mil. € | 6 651 - 9 113 | 2 | ||||
4 | 24. | 12/2025 | R2 | 6,1 km | 4 | Trenčín juh, Trenčianska Turná | 143 mil. € | 12 157 | 3 | |||||
5 | 19. | 6/2025 | R4 | 8,2 km | 2 | Svidník sever | 94 mil. € | 4 001 | 3 | |||||
6 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | Trenčianske Mitice | 277 mil. € | 9 654 - 12 079 | 2 | |||||
7 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | Podbiel | 199 mil. € | 5 550 - 9 787 | 2 | |||||
8 | 18. | 4/2025 | D1 | 1,1 km | 2 | 12 mil. € | 2 | |||||||
9 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | Okrúhle | 122 mil. € | 3 407 - 3 769 | 2 | |||||
10 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 1 | 59 mil. € | 12 862 | 3 | |||||
71,3 km |
2 - 8 |
2 |
1 332 mil. € |
3 407 - 62 652 | 2,3 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku