plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||||||
1 | D4 | 12,4 km | 4 | Karpaty 10 990 m | 772 mil. € | 3 | 4 | 6/2033 (+3,3) | |||||||
2 | D3 | 10,8 km | 4 | 2 060 m | 309 mil. € | 14 176 - 14 186 | 2 | 4 | 7/2022 | 1/2029 (+3,0) | |||||
3 | R4 | 4,0 km | 4 | 2 045 m | 105 mil. € | 14 625 | 2 | 2 | 8/2029 (+3,8) | ||||||
4 | R2 | 20,7 km | 2 | 3 480 m | 211 mil. € | 6 969 - 10 726 | 4 | 4 | 4/2028 (+4,8) | ||||||
5 | R2 | 18,0 km | 2 | 16 837 m | 224 mil. € | 10 140 - 11 010 | 3 | 5 | 12/2029 (+2,8) | ||||||
6 | D3 | 4,0 km | 4 | Horelica 590 m | 624 m | 179 mil. € | 15 053 | 1 | 2 | 11/2030 (+6,4) | |||||
7 | R2 | 10,6 km | 2 | 1 295 m | 125 mil. € | 6 412 - 8 112 | 4 | 4 | 8/2028 (+5,1) | ||||||
8 | R1 | 4,6 km | 4 | 2 982 m | 100 mil. € | 11 611 | 4 | 3 | 10/2028 (+3,5) | ||||||
9 | D3 | 11,2 km | 4 | 3 896 m | 410 mil. € | 13 886 - 21 743 | 1 | 1 | 5/2022 | 5/2029 (+5,1) | |||||
9 úsekov |
96,3 km |
2 - 4 |
33 219 m |
2 435 mil. € |
6 412 - 21 743 | 2,7 |
3,2 |
4/2028 - 6/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku