plánovaný
|
odhad NDS
|
3,5 - 12 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
||||||
1 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 6/2033 (+3,3) | ||||
2 | D3 | 10,8 km | 4 | 309 mil. € | 381 - 551 | 2 | 4 | 1/2029 (+3,0) | |||
3 | R4 | 4,0 km | 4 | 105 mil. € | 408 | 2 | 2 | 8/2029 (+3,8) | |||
4 | R2 | 20,7 km | 2 | 211 mil. € | 280 - 373 | 4 | 4 | 4/2028 (+4,8) | |||
5 | R2 | 18,0 km | 2 | 224 mil. € | 299 - 336 | 3 | 5 | 12/2029 (+2,8) | |||
6 | D3 | 4,0 km | 4 | 179 mil. € | 588 | 1 | 2 | 11/2030 (+6,4) | |||
7 | R2 | 10,6 km | 2 | 125 mil. € | 193 - 261 | 4 | 4 | 8/2028 (+5,1) | |||
8 | R1 | 4,6 km | 4 | 100 mil. € | 213 | 4 | 3 | 10/2028 (+3,5) | |||
9 | D3 | 11,2 km | 4 | 410 mil. € | 426 - 554 | 1 | 1 | 5/2029 (+5,1) | |||
9 úsekov |
96,3 km |
2 - 4 |
2 435 mil. € |
2,7 |
3,2 |
4/2028 - 6/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku