dátum |
plánovaný
|
odhad NDS
|
>12 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
18 úsekov |
154,0 km |
2 - 4 |
3 767 mil. € |
4 001 - 21 988 | 2,4 |
2,8 |
1/2021 - 10/2021 | ||||||||||
1 | 6/2017 | ![]() | D1 | 7,9 km | 4 | 434 mil. € | 19 072 - 21 988 | 1 186 - 1 322 | 1 | 2 | 11/2013 | 10/2021 | |||||
2 | 12/2017 | ![]() | D1 | 2,6 km | 4 | 39 mil. € | 14 624 | 789 | 1 | 1 | 10,0 | 12/2014 | 1/2021 (0,0) | ||||
3 | 18. | 4/2025 | ![]() | D1 | 1,1 km | 2 | 12 mil. € | 2 | 1 | 7,0 | 12/2016 | ||||||
4 | 19. | 6/2025 | ![]() | R4 | 8,2 km | 2 | 94 mil. € | 4 001 | 1 361 | 3 | 3 | 7,0 | 12/2017 | ||||
5 | 20. - 23. | 10/2025 | ![]() | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2 | 6,0 | 1/2023 | ||||||
6 | 20. - 23. | 10/2025 | ![]() | R3 | 8,3 km | 2 | 199 mil. € | 5 550 - 9 787 | 526 - 829 | 2 | 3 | 6,0 | 1/2023 | ||||
7 | 20. - 23. | 10/2025 | ![]() | R2 | 16,0 km | 4 | 277 mil. € | 9 654 - 12 079 | 1 040 - 1 450 | 2 | 2 | 6,0 | 9/2023 | ||||
8 | 20. - 23. | 10/2025 | ![]() | R2 | 2,7 km | 4 | 59 mil. € | 12 862 | 1 313 | 3 | 4 | 6,0 | 10/2022 | ||||
9 | 24. | 12/2025 | ![]() | R2 | 6,1 km | 4 | 143 mil. € | 12 157 | 1 263 | 3 | 4 | 7,0 | 2/2023 | ||||
10 | 25. | 1/2026 | ![]() | D3 | 10,8 km | 4 | 309 mil. € | 14 176 - 14 186 | 2 105 - 2 649 | 2 | 4 | 6,0 | 8/2010 | ||||
11 | 26. | 4/2026 | ![]() | R2 | 20,7 km | 2 | 211 mil. € | 6 969 - 10 726 | 863 - 1 016 | 4 | 4 | 5,0 | 11/2023 | ||||
12 | 27. | 5/2026 | ![]() | D3 | 11,2 km | 4 | 410 mil. € | 13 886 - 21 743 | 2 661 - 2 869 | 1 | 1 | 7,0 | 2000/ 2007/ 2011 | ||||
13 | 28. - 29. | 8/2026 | ![]() | R4 | 4,0 km | 4 | 105 mil. € | 14 625 | 1 056 | 2 | 2 | 5,0 | 12/2023 | ||||
14 | 28. - 29. | 8/2026 | ![]() | R2 | 10,6 km | 2 | 125 mil. € | 6 412 - 8 112 | 655 - 822 | 4 | 4 | 5,0 | 3/2024 | ||||
15 | 30. | 10/2026 | ![]() | R1 | 4,6 km | 4 | 100 mil. € | 11 611 | 693 | 4 | 3 | 3,0 | 7/2025 | ||||
16 | 31. | 11/2026 | ![]() | D3 | 4,0 km | 4 | 179 mil. € | 15 053 | 2 660 | 1 | 2 | 7,0 | 12/2021 | ||||
17 | 32. - 33. | 12/2026 | ![]() | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 4,0 | |||||||
18 | 32. - 33. | 12/2026 | ![]() | R2 | 18,0 km | 2 | 224 mil. € | 10 140 - 11 010 | 792 - 846 | 3 | 5 | 5,0 | 12/2023 | ||||
18 úsekov |
154,0 km |
2 - 4 |
3 767 mil. € |
4 001 - 21 988 | 2,4 |
2,8 |
1/2021 - 10/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku