dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
16 úsekov |
143,6 km |
2 - 4 |
3 295 mil. € |
4 001 - 21 743 | 2,6 |
3,0 |
1/2027 - 6/2033 |
|||||||||
1 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | Moldava nad Bodvou, Šaca | 224 mil. € | 10 140 - 11 010 | 3 | 5 | 12/2029 | |||||
2 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 6/2033 | |||||||
3 | 31. | 11/2026 | D3 | 4,0 km | 4 | 179 mil. € | 15 053 | 1 | 2 | 11/2030 | ||||||
4 | 30. | 10/2026 | R1 | 4,6 km | 4 | križovatka D1 | 100 mil. € | 11 611 | 4 | 3 | 10/2028 | |||||
5 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | Rimavská Sobota | 125 mil. € | 6 412 - 8 112 | 4 | 4 | 8/2028 | |||||
6 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | Lipníky | 105 mil. € | 14 625 | 2 | 2 | 8/2029 | |||||
7 | 27. | 5/2026 | D3 | 11,2 km | 4 | Brodno, Kysucké Nové Mesto | 410 mil. € | 13 886 - 21 743 | 1 | 1 | 5/2029 | |||||
8 | 26. | 4/2026 | R2 | 20,7 km | 2 | 211 mil. € | 6 969 - 10 726 | 4 | 4 | 4/2028 | ||||||
9 | 25. | 1/2026 | D3 | 10,8 km | 4 | Krásno nad Kysucou | 309 mil. € | 14 176 - 14 186 | 2 | 4 | 1/2029 | |||||
10 | 24. | 12/2025 | R2 | 6,1 km | 4 | Trenčín juh, Trenčianska Turná | 143 mil. € | 12 157 | 3 | 4 | 12/2028 | |||||
11 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | Trenčianske Mitice | 277 mil. € | 9 654 - 12 079 | 2 | 2 | 10/2028 | |||||
12 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 59 mil. € | 12 862 | 3 | 4 | 10/2028 | ||||||
13 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | Dlhá nad Oravou | 77 mil. € | 2 | 2 | 10/2028 | ||||||
14 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | Podbiel | 199 mil. € | 5 550 - 9 787 | 2 | 3 | 10/2028 | |||||
15 | 19. | 6/2025 | R4 | 8,2 km | 2 | Svidník sever | 94 mil. € | 4 001 | 3 | 3 | 6/2027 | |||||
16 | 18. | 4/2025 | D1 | 1,1 km | 2 | 12 mil. € | 2 | 1 | 1/2027 | |||||||
16 úsekov |
143,6 km |
2 - 4 |
3 295 mil. € |
4 001 - 21 743 | 2,6 |
3,0 |
1/2027 - 6/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku