dátum |
plánovaný
|
odhad NDS
|
<3,5 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
16 úsekov |
172,9 km |
2 - 6 |
4 152 mil. € |
2 552 - 54 519 | 2,9 |
3,2 |
|||||||||||
1 | 25. | 1/2026 | D3 | 10,8 km | 4 | D 24,5/80 (100) | 309 mil. € | 14 176 - 14 186 | 875 - 929 | 2 | 4 | 2/2024 | |||||
2 | 26. | 4/2026 | R2 | 20,7 km | 2 | R 24,5/120, plánované v 1/2-profile | 211 mil. € | 6 969 - 10 726 | 557 - 946 | 4 | 4 | ||||||
3 | 27. | 5/2026 | D3 | 11,2 km | 4 | D 24,5/80 | 410 mil. € | 13 886 - 21 743 | 738 - 1 705 | 1 | 1 | 4/2024 | |||||
4 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | R 24,5/100 | 105 mil. € | 14 625 | 888 | 2 | 2 | ||||||
5 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | R 22,5/100, plánované v 1/2-profile | 125 mil. € | 6 412 - 8 112 | 516 - 606 | 4 | 4 | ||||||
6 | 30. | 10/2026 | R1 | 4,6 km | 4 | R 24,5/80 | 100 mil. € | 11 611 | 623 | 4 | 3 | ||||||
7 | 31. | 11/2026 | D3 | 4,0 km | 4 | D 24,5/80 | 179 mil. € | 15 053 | 1 018 | 1 | 2 | 2/2024 | |||||
8 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | D 26,5/120 (tunel 2 x T 8,0/100) | 772 mil. € | 3 | 4 | ||||||||
9 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 224 mil. € | 10 140 - 11 010 | 570 - 674 | 3 | 5 | ||||||
10 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | R 24,5/80 | 785 mil. € | 8 140 - 13 204 | 575 - 1 052 | 3 | 3 | ||||||
11 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | R 24,5/120, plánované v 1/2-profile | 73 mil. € | 5 587 | 488 | 5 | 4 | ||||||
12 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | D 33,5/120 | 321 mil. € | 42 774 - 54 519 | . . . | 2 765 - 3 271 | 3 | 2 | 7/2025 | ||||
13 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 112 mil. € | 8 634 - 11 116 | 635 - 690 | 2 | 4 | ||||||
14 | 41. | 9/2028 | R2 | 11,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 235 mil. € | 7 793 | 655 | 2 | 4 | ||||||
15 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | R 24,5/100, plánované v 1/2-profile | 129 mil. € | 2 552 - 2 737 | 177 - 189 | 4 | 3 | ||||||
16 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 63 mil. € | 9 492 - 10 279 | 332 - 531 | 3 | 2 | ||||||
16 úsekov |
172,9 km |
2 - 6 |
4 152 mil. € |
2 552 - 54 519 | 2,9 |
3,2 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku