✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | |||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
# |
dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||||
1 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 176 mil. € | 5 189 - 6 389 | 5 | 5 | 5/2027 | ||||||
2 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | D 26,5/100 | 133 mil. € | 5 | 5 | ||||||||
3 | 46. | 3/2029 | D1 | 7,3 km | 4 | 26,5/100 | 321 mil. € | 10 359 | 3 | 3 | 12/2027 | ||||||
4 | 47. | 7/2029 | R2 | 14,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 117 mil. € | 5 809 - 8 826 | 5 | 4 | 10/2027 | ||||||
5 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | R 24,5/120, plánované v 1/2-profile | 93 mil. € | 6 452 - 10 032 | 5 | 5 | 12/2027 | ||||||
6 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 71 mil. € | 5 441 - 8 427 | 4 | 3 | 12/2018 | 5/2028 | |||||
6 úsekov |
60,5 km |
2 - 4 |
910 mil. € |
5 189 - 10 359 | 4,5 |
4,2 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku