dátum |
plánovaný
|
jednostranné / obojstranné
|
odhad NDS
|
<3,5 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
20 úsekov |
200,8 km |
2 - 4 |
4 107 mil. € |
2 561 - 21 743 | 3,5 |
3,5 |
1/2026 - 7/2030 |
||||||||||
1 | 25. | 1/2026 | ![]() | D3 | 10,8 km | 4 | Krásno nad Kysucou a Oščadnica (obe jednostranné) | 309 mil. € | 14 176 - 14 186 | 875 - 929 | 2 | 4 | 1/2026 | ||||
2 | 26. | 4/2026 | ![]() | R2 | 20,7 km | 2 | 211 mil. € | 6 969 - 10 726 | 557 - 946 | 4 | 4 | 4/2026 | |||||
3 | 27. | 5/2026 | ![]() | D3 | 11,2 km | 4 | 410 mil. € | 13 886 - 21 743 | 738 - 1 705 | 1 | 1 | 5/2026 | |||||
4 | 28. - 29. | 8/2026 | ![]() | R4 | 4,0 km | 4 | 105 mil. € | 14 625 | 888 | 2 | 2 | 8/2026 | |||||
5 | 28. - 29. | 8/2026 | ![]() | R2 | 10,6 km | 2 | 125 mil. € | 6 412 - 8 112 | 516 - 606 | 4 | 4 | 8/2026 | |||||
6 | 30. | 10/2026 | ![]() | R1 | 4,6 km | 4 | 100 mil. € | 11 611 | 623 | 4 | 3 | 10/2026 | |||||
7 | 31. | 11/2026 | ![]() | D3 | 4,0 km | 4 | 179 mil. € | 15 053 | 1 018 | 1 | 2 | 11/2026 | |||||
8 | 32. - 33. | 12/2026 | ![]() | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 12/2026 | |||||||
9 | 32. - 33. | 12/2026 | ![]() | R2 | 18,0 km | 2 | 224 mil. € | 10 140 - 11 010 | 570 - 674 | 3 | 5 | 12/2026 | |||||
10 | 44. - 45. | 2/2029 | ![]() | R2 | 18,0 km | 2 | Gombasek | 176 mil. € | 5 189 - 6 389 | 359 - 396 | 5 | 5 | 2/2029 | ||||
11 | 44. - 45. | 2/2029 | ![]() | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 2/2029 | |||||||
12 | 46. | 3/2029 | ![]() | D1 | 7,3 km | 4 | 321 mil. € | 10 359 | 974 | 3 | 3 | 3/2029 | |||||
13 | 47. | 7/2029 | ![]() | R2 | 14,0 km | 2 | Drienovec | 117 mil. € | 5 809 - 8 826 | 454 - 531 | 5 | 4 | 7/2029 | ||||
14 | 48. - 49. | 9/2029 | ![]() | R2 | 9,8 km | 2 | 93 mil. € | 6 452 - 10 032 | 473 - 644 | 5 | 5 | 9/2029 | |||||
15 | 48. - 49. | 9/2029 | ![]() | R3 | 7,9 km | 2 | 71 mil. € | 5 441 - 8 427 | 423 - 703 | 4 | 3 | 9/2029 | |||||
16 | 50. - 52. | 5/2030 | ![]() | R4 | 8,0 km | 2 | 133 mil. € | 5 814 - 7 518 | 384 - 424 | 4 | 3 | 5/2030 | |||||
17 | 50. - 52. | 5/2030 | ![]() | R4 | 7,5 km | 2 | 124 mil. € | 3 769 - 3 897 | 240 - 264 | 3 | 3 | 5/2030 | |||||
18 | 50. - 52. | 5/2030 | ![]() | R4 | 6,0 km | 2 | 101 mil. € | 3 782 - 6 302 | 205 - 412 | 4 | 3 | 5/2030 | |||||
19 | 53. - 54. | 7/2030 | ![]() | R6 | 11,2 km | 2 | 182 mil. € | 7 234 | 426 | 4 | 3 | 7/2030 | |||||
20 | 53. - 54. | 7/2030 | ![]() | R6 | 11,3 km | 2 | Strelenka, obojstranné | 222 mil. € | 2 561 - 5 054 | 146 - 252 | 4 | 3 | 7/2030 | ||||
20 úsekov |
200,8 km |
2 - 4 |
4 107 mil. € |
2 561 - 21 743 | 3,5 |
3,5 |
1/2026 - 7/2030 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku