dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
prebratie
|
+ posun v rokoch
za posledné cca 4 roky | |||||||||||
14 úsekov |
140,3 km |
2 - 4 |
3 197 mil. € |
2 561 - 21 743 | 3,1 |
3,1 |
4/2028 - 7/2033 |
|||||||||||
1 | 26. | 4/2026 | R2 | 20,7 km | 2 | R 24,5/120, plánované v 1/2-profile | 211 mil. € | 6 969 - 10 726 | 4 | 4 | 7/2014 | 4/2028 (+4,8) | ||||||
2 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 224 mil. € | 10 140 - 11 010 | 3 | 5 | 12/2014 | 12/2029 (+2,8) | ||||||
3 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | D 26,5/120 (tunel 2 x T 8,0/100) | Karpaty 10 990 m | 772 mil. € | 3 | 4 | 9/2009 | 6/2033 (+3,3) | ||||||
4 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | R 11,5/100 (80) | 222 mil. € | 2 561 - 5 054 | 4 | 3 | 2/2016 | 7/2033 (+4,3) | ||||||
5 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | R 11,5/100 (80) | 182 mil. € | 7 234 | 4 | 3 | 2/2016 | 7/2033 (+4,3) | ||||||
6 | 27. | 5/2026 | D3 | 11,2 km | 4 | D 24,5/80 | 410 mil. € | 13 886 - 21 743 | 1 | 1 | 6/2014 | 5/2029 (+5,1) | ||||||
7 | 25. | 1/2026 | D3 | 10,8 km | 4 | D 24,5/80 (100) | 309 mil. € | 14 176 - 14 186 | 2 | 4 | 6/2014 | 1/2029 (+3,0) | ||||||
8 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | R 22,5/100, plánované v 1/2-profile | 125 mil. € | 6 412 - 8 112 | 4 | 4 | 6/2014 | 8/2028 (+5,1) | ||||||
9 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | R 24,5/100, plánované v 1/2-profile | 133 mil. € | 5 814 - 7 518 | 4 | 3 | 12/2014 | 5/2033 (+6,1) | ||||||
10 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | R 24,5/100, plánované v 1/2-profile | 124 mil. € | 3 769 - 3 897 | 3 | 3 | 12/2014 | 5/2033 (+6,1) | ||||||
11 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | R 24,5/100, plánované v 1/2-profile | 101 mil. € | 3 782 - 6 302 | 4 | 3 | 12/2014 | 5/2033 (+6,1) | ||||||
12 | 30. | 10/2026 | R1 | 4,6 km | 4 | R 24,5/80 | 100 mil. € | 11 611 | 4 | 3 | 8/2015 | 10/2028 (+3,5) | ||||||
13 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | R 24,5/100 | 105 mil. € | 14 625 | 2 | 2 | 12/2014 | 8/2029 (+3,8) | ||||||
14 | 31. | 11/2026 | D3 | 4,0 km | 4 | D 24,5/80 | Horelica 590 m | 179 mil. € | 15 053 | 1 | 2 | 6/2014 | 11/2030 (+6,4) | |||||
14 úsekov |
140,3 km |
2 - 4 |
3 197 mil. € |
2 561 - 21 743 | 3,1 |
3,1 |
4/2028 - 7/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku