dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | 234 mil. € | 6,1 mil. € | 62 652 | . . . | 2 | 1 | ||||
2 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | 116 mil. € | 2,8 mil. € | 6 651 - 9 113 | 2 | 3 | 28. | ||||
3 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | 122 mil. € | 3,1 mil. € | 3 407 - 3 769 | 2 | 2 | 32. | ||||
4 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 3,5 mil. € | 5 814 - 7 518 | 4 | 3 | 91. | ||||
5 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 124 mil. € | 3,3 mil. € | 3 769 - 3 897 | 3 | 3 | 45. | ||||
6 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 2,6 mil. € | 3 782 - 6 302 | 4 | 3 | 80. | ||||
7 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 182 mil. € | 4,8 mil. € | 7 234 | 4 | 3 | 17. | ||||
8 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 6,0 mil. € | 2 561 - 5 054 | 4 | 3 | 14. | ||||
68,1 km |
2 - 8 |
1 234 mil. € |
32,2 mil. € |
2 561 - 62 652 | 3,1 |
2,6 |
14. - 91. |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku