dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 2 561 - 5 054 | 427 - 551 | 4 | 3 | ||||||
2 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 0,8 min. | 3 782 - 6 302 | 1 492 - 1 737 | 4 | 3 | |||||
3 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | 122 mil. € | 4,8 min. | 3 407 - 3 769 | 1 298 - 1 289 | 2 | 2 | |||||
4 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 124 mil. € | 2,8 min. | 3 769 - 3 897 | 1 289 - 1 580 | 3 | 3 | |||||
5 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 182 mil. € | 7 234 | 632 | 4 | 3 | ||||||
6 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 1,6 min. | 5 814 - 7 518 | 349 - 902 | 4 | 3 | |||||
7 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | 116 mil. € | 4,2 min. | 6 651 - 9 113 | 750 - 771 | 2 | 3 | |||||
8 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | 234 mil. € | 62 652 | . . . | 6 104 | 2 | 1 | |||||
8 úsekov |
68,1 km |
2 - 8 |
1 234 mil. € |
14,1 min. |
2 561 - 62 652 | 3,1 |
2,6 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku