dátum |
plánovaný
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||||
18 úsekov |
151,7 km |
2 - 4 |
2 561 - 12 862 | 3,5 |
3,3 |
4/2024 - 11/2029 |
1/2027 - 9/2033 |
|||||||||
1 | 18. | 4/2025 | D1 | 1,1 km | 2 | 4 984 | 2 | 1 | 4/2024 | 1/2027 (+5,0) | ||||||
2 | 19. | 6/2025 | R4 | 8,2 km | 2 | 6 944 | 4 001 | 3 | 3 | 6/2024 | 6/2027 (+4,7) | |||||
3 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 5 660 | 2 | 2 | 2/2025 | 10/2028 (+4,1) | ||||||
4 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | 6 090 | 5 550 - 9 787 | 2 | 3 | 2/2025 | 10/2028 (+4,1) | |||||
5 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 12 676 - 16 847 | 9 654 - 12 079 | 2 | 2 | 2/2025 | 10/2028 (+3,2) | |||||
6 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 13 396 | 12 862 | 3 | 4 | 2/2025 | 10/2028 (+4,2) | |||||
7 | 24. | 12/2025 | R2 | 6,1 km | 4 | 12 125 | 12 157 | 3 | 4 | 4/2025 | 12/2028 (+4,3) | |||||
8 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 8 348 | 5 189 - 6 389 | 5 | 5 | 2/2028 | 2/2032 (+4,9) | |||||
9 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | NDS údaj neposkytla | 5 | 5 | 6/2028 | 2/2033 (+4,5) | ||||||
10 | 46. | 3/2029 | D1 | 7,3 km | 4 | 17 042 | 10 359 | 3 | 3 | 7/2028 | 9/2033 (+5,8) | |||||
11 | 47. | 7/2029 | R2 | 14,0 km | 2 | 15 407 | 5 809 - 8 826 | 5 | 4 | 7/2028 | 7/2032 (+5,3) | |||||
12 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 10 783 | 6 452 - 10 032 | 5 | 5 | 9/2028 | 9/2032 (+5,6) | |||||
13 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 12 145 - 15 746 | 5 441 - 8 427 | 4 | 3 | 1/2029 | 9/2032 (+4,1) | |||||
14 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 8 195 | 5 814 - 7 518 | 4 | 3 | 5/2029 | 5/2033 (+6,1) | |||||
15 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 7 637 | 3 769 - 3 897 | 3 | 3 | 5/2029 | 5/2033 (+6,1) | |||||
16 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 8 391 | 3 782 - 6 302 | 4 | 3 | 5/2029 | 5/2033 (+6,1) | |||||
17 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 5 938 - 12 956 | 7 234 | 4 | 3 | 11/2029 | 7/2033 (+4,3) | |||||
18 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 1 942 - 3 996 | 2 561 - 5 054 | 4 | 3 | 11/2029 | 7/2033 (+4,3) | |||||
18 úsekov |
151,7 km |
2 - 4 |
2 561 - 12 862 | 3,5 |
3,3 |
4/2024 - 11/2029 |
1/2027 - 9/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku