dátum |
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
prebratie
|
+ posun v rokoch
za posledné cca 4 roky | |||||||||||
1 | 50. - 52. | 5/2030 | R4 | 8,0 km | R 24,5/100, plánované v 1/2-profile | 133 mil. € | 5 814 - 7 518 | 4 | 3 | 12/2014 | 5/2033 (+6,1) | ||||||
2 | 50. - 52. | 5/2030 | R4 | 7,5 km | R 24,5/100, plánované v 1/2-profile | 124 mil. € | 3 769 - 3 897 | 3 | 3 | 12/2014 | 5/2033 (+6,1) | ||||||
3 | 50. - 52. | 5/2030 | R4 | 6,0 km | R 24,5/100, plánované v 1/2-profile | 101 mil. € | 3 782 - 6 302 | 4 | 3 | 12/2014 | 5/2033 (+6,1) | ||||||
4 | 53. - 54. | 7/2030 | R6 | 11,2 km | R 11,5/100 (80) | 182 mil. € | 7 234 | 4 | 3 | 2/2016 | 7/2033 (+4,3) | ||||||
5 | 53. - 54. | 7/2030 | R6 | 11,3 km | R 11,5/100 (80) | 222 mil. € | 2 561 - 5 054 | 4 | 3 | 2/2016 | 7/2033 (+4,3) | ||||||
6 | 62. - 63. | 10/2032 | D2 | 8,5 km | D 33,5/120 | 90 mil. € | 32 968 | . . . | 5 | 5 | 3/2016 | 10/2035 (+5,6) | |||||
7 | 62. - 63. | 10/2032 | D2 | 6,9 km | D 33,5/120 | 107 mil. € | 5 | 5 | 3/2016 | 10/2035 (+5,9) | |||||||
7 úsekov |
59,4 km |
959 mil. € |
2 561 - 32 968 | 4,1 |
3,6 |
5/2033 - 10/2035 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku