dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||||
1 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | 406 mil. € | 7 784 | 4 | 4 | 11/2026 | 7/2030 | 5/2033 | ||||||
2 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 339 mil. € | 9 704 - 13 715 | 4 | 4 | 11/2026 | 7/2030 | 5/2033 | ||||||
3 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | 1 020 mil. € | 4 151 - 11 477 | 3 | 5 | 12/2026 | 7/2030 | 6/2036 | ||||||
4 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 191 mil. € | 14 233 - 18 874 | 3 | 3 | 3/2027 | 8/2030 | 6/2034 | ||||||
5 | 59. | 7/2031 | R2 | 17,5 km | 4 | 287 mil. € | 12 819 - 29 988 | 2 | 2 | 2/2026 | 8/2030 | 7/2034 | ||||||
6 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | 94 mil. € | 7 211 | 4 | 2 | 3/2026 | 9/2030 | 8/2034 | ||||||
7 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | 129 mil. € | 5 586 - 10 745 | 3 | 2 | 3/2026 | 9/2030 | 8/2034 | ||||||
8 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | 90 mil. € | 32 968 | . . . | 5 | 5 | 3/2027 | 9/2031 | 10/2035 | |||||
9 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | 107 mil. € | 5 | 5 | 3/2027 | 9/2031 | 10/2035 | |||||||
9 úsekov |
142,4 km |
2 - 6 |
2 663 mil. € |
4 151 - 32 968 | 3,7 |
3,6 |
5/2033 - 6/2036 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku