dátum |
plánovaný
|
odhad NDS
|
>12 t
|
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | 90 mil. € | 32 968 | . . . | 5 960 | 5 | 9,0 | 2/2032 | ||||
2 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | 107 mil. € | 5 | 9,0 | 2/2032 | |||||||
3 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 5 814 - 7 518 | 142 - 701 | 3 | 6,0 | 5/2029 | |||||
4 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 182 mil. € | 7 234 | 394 | 3 | 8,0 | 11/2029 | |||||
5 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 124 mil. € | 3 769 - 3 897 | 1 149 - 1 405 | 3 | 6,0 | 5/2029 | |||||
6 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 3 782 - 6 302 | 1 375 - 1 435 | 3 | 6,0 | 5/2029 | |||||
7 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 2 561 - 5 054 | 292 - 307 | 3 | 8,0 | 11/2029 | |||||
7 úsekov |
59,4 km |
2 - 6 |
959 mil. € |
2 561 - 32 968 | 3,6 |
5/2029 - 2/2032 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku