dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
21 úsekov |
198,5 km |
2 - 6 |
3 188 mil. € |
1 698 - 32 968 | 3,1 |
3,0 |
|||||||||
1 | 64. - 68. | 8/2033 | ![]() | D1 | 12,6 km | 4 | 418 mil. € | 9 503 - 9 802 | 3 | 3 | 11/2031 | ||||
2 | 64. - 68. | 8/2033 | ![]() | D1 | 18,2 km | 4 | 192 mil. € | 6 207 - 8 525 | 2 | 2 | 11/2031 | ||||
3 | 20. - 23. | 10/2025 | ![]() | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2 | 6/2024 | |||||
4 | 24. | 12/2025 | ![]() | R2 | 6,1 km | 4 | 143 mil. € | 12 157 | 3 | 4 | 5/2024 | ||||
5 | 50. - 52. | 5/2030 | ![]() | R4 | 8,0 km | 2 | 133 mil. € | 5 814 - 7 518 | 4 | 3 | 8/2028 | ||||
6 | 19. | 6/2025 | ![]() | R4 | 8,2 km | 2 | 94 mil. € | 4 001 | 3 | 3 | 10/2023 | ||||
7 | 62. - 63. | 10/2032 | ![]() | D2 | 8,5 km | 6 | 90 mil. € | 32 968 | . . . | 5 | 5 | 4/2031 | |||
8 | 53. - 54. | 7/2030 | ![]() | R6 | 11,2 km | 2 | 182 mil. € | 7 234 | 4 | 3 | 5/2029 | ||||
9 | 64. - 68. | 8/2033 | ![]() | D1 | 15,8 km | 4 | 139 mil. € | 4 033 - 8 369 | 4 | 3 | 11/2031 | ||||
10 | 20. - 23. | 10/2025 | ![]() | R2 | 16,0 km | 4 | 277 mil. € | 9 654 - 12 079 | 2 | 2 | 8/2024 | ||||
11 | 8/2019 | ![]() | R2 | 13,5 km | 4 | 142 mil. € | 9 007 - 9 998 | 2 | 2 | 12/2018 | |||||
12 | 20. - 23. | 10/2025 | ![]() | R3 | 8,3 km | 2 | 199 mil. € | 5 550 - 9 787 | 2 | 3 | 6/2024 | ||||
13 | 64. - 68. | 8/2033 | ![]() | D1 | 12,1 km | 4 | 162 mil. € | 10 444 - 14 783 | 3 | 3 | 11/2031 | ||||
14 | 7/2019 | ![]() | R4 | 4,3 km | 4 | 179 mil. € | 15 837 - 18 098 | 1 | 3 | 1/2017 | |||||
15 | 18. | 4/2025 | ![]() | D1 | 1,1 km | 2 | 12 mil. € | 2 | 1 | 10/2023 | |||||
16 | 50. - 52. | 5/2030 | ![]() | R4 | 7,5 km | 2 | 124 mil. € | 3 769 - 3 897 | 3 | 3 | 8/2028 | ||||
17 | 64. - 68. | 8/2033 | ![]() | D1 | 15,5 km | 4 | 136 mil. € | 1 698 - 6 812 | 4 | 3 | 11/2031 | ||||
18 | 62. - 63. | 10/2032 | ![]() | D2 | 6,9 km | 6 | 107 mil. € | 5 | 5 | 4/2031 | |||||
19 | 50. - 52. | 5/2030 | ![]() | R4 | 6,0 km | 2 | 101 mil. € | 3 782 - 6 302 | 4 | 3 | 8/2028 | ||||
20 | 20. - 23. | 10/2025 | ![]() | R2 | 2,7 km | 4 | 59 mil. € | 12 862 | 3 | 4 | 11/2023 | ||||
21 | 53. - 54. | 7/2030 | ![]() | R6 | 11,3 km | 2 | 222 mil. € | 2 561 - 5 054 | 4 | 3 | 5/2029 | ||||
21 úsekov |
198,5 km |
2 - 6 |
3 188 mil. € |
1 698 - 32 968 | 3,1 |
3,0 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku