dátum |
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
150,7 km |
2 764 mil. € |
91,0 min. |
19,8 min. |
1 698 - 54 519 | 3,2 |
3,0 |
|||||||||
1 | 64. - 68. | 8/2033 | D1 | 12,6 km | 418 mil. € | 12,0 min. | 3,1 min. | 9 503 - 9 802 | 3 | 3 | |||||
2 | 64. - 68. | 8/2033 | D1 | 18,2 km | 192 mil. € | 17,0 min. | 4,2 min. | 6 207 - 8 525 | 2 | 2 | |||||
3 | 64. - 68. | 8/2033 | D1 | 15,8 km | 139 mil. € | 16,0 min. | 5,6 min. | 4 033 - 8 369 | 4 | 3 | |||||
4 | 64. - 68. | 8/2033 | D1 | 12,1 km | 162 mil. € | 8,0 min. | -0,3 min. | 10 444 - 14 783 | 3 | 3 | |||||
5 | 64. - 68. | 8/2033 | D1 | 15,5 km | 136 mil. € | 15,0 min. | 4,1 min. | 1 698 - 6 812 | 4 | 3 | |||||
6 | 42. - 43. | 11/2028 | R3 | 5,0 km | 63 mil. € | 9 492 - 10 279 | 3 | 2 | 11/2018 | ||||||
7 | 42. - 43. | 11/2028 | R4 | 7,9 km | 129 mil. € | 7,0 min. | 0,8 min. | 2 552 - 2 737 | 4 | 3 | 4/2016 | ||||
8 | 41. | 9/2028 | R2 | 11,5 km | 235 mil. € | 11,0 min. | 2,9 min. | 7 793 | 2 | 4 | 10/2004 | ||||
9 | 39. - 40. | 3/2028 | R2 | 9,6 km | 112 mil. € | 8 634 - 11 116 | 2 | 4 | 10/2004 | ||||||
10 | 39. - 40. | 3/2028 | D1 | 19,9 km | 321 mil. € | 42 774 - 54 519 | . . . | 3 | 2 | 12/2009 | |||||
11 | 37. - 38. | 2/2028 | R2 | 7,8 km | 73 mil. € | 5,0 min. | -0,5 min. | 5 587 | 5 | 4 | 9/2009 | ||||
12 | 37. - 38. | 2/2028 | R1 | 14,9 km | 785 mil. € | 8 140 - 13 204 | 3 | 3 | 4/2010 | ||||||
150,7 km |
2 764 mil. € |
91,0 min. |
19,8 min. |
1 698 - 54 519 | 3,2 |
3,0 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku