dátum |
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||||
1 | 69. - 70. | 8/2034 | R2 | 49,0 km | 662 mil. € | 5,5 mil. € | 5 762 - 14 648 | 4 | 4 | 8/2037 (+5,9) | ||||
2 | 69. - 70. | 8/2034 | R3 | 14,0 km | 305 mil. € | 5,0 mil. € | 3 | 3 | 8/2037 (+5,9) | |||||
3 | 53. - 54. | 7/2030 | R6 | 11,3 km | 222 mil. € | 5,7 mil. € | 2 561 - 5 054 | 4 | 3 | 7/2033 (+4,3) | ||||
4 | 53. - 54. | 7/2030 | R6 | 11,2 km | 182 mil. € | 6,2 mil. € | 7 234 | 4 | 3 | 7/2033 (+4,3) | ||||
5 | 50. - 52. | 5/2030 | R4 | 8,0 km | 133 mil. € | 5,8 mil. € | 5 814 - 7 518 | 4 | 3 | 5/2033 (+6,1) | ||||
6 | 50. - 52. | 5/2030 | R4 | 7,5 km | 124 mil. € | 6,2 mil. € | 3 769 - 3 897 | 3 | 3 | 5/2033 (+6,1) | ||||
7 | 50. - 52. | 5/2030 | R4 | 6,0 km | 101 mil. € | 5,5 mil. € | 3 782 - 6 302 | 4 | 3 | 5/2033 (+6,1) | ||||
7 úsekov |
107,0 km |
1 729 mil. € |
39,9 mil. € |
2 561 - 14 648 | 3,7 |
3,1 |
5/2033 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku