dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
1 | 46. | 3/2029 | D1 | 7,3 km | 4 | 660 m | 321 mil. € | 4,6 min. | 3 | 3 | ||||
2 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | ||||||
3 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 1 074 m | 93 mil. € | 6,2 min. | 5 | 5 | ||||
4 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | 2 641 m | 305 mil. € | 3 | 3 | |||||
5 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 820 m | 71 mil. € | 4 | 3 | |||||
6 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | 2 587 m | 662 mil. € | 4 | 4 | |||||
7 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 1 739 m | 176 mil. € | 11,1 min. | 5 | 5 | ||||
8 | 47. | 7/2029 | R2 | 14,0 km | 2 | 768 m | 117 mil. € | 8,8 min. | 5 | 4 | ||||
8 úsekov |
123,5 km |
2 - 4 |
10 289 m |
1 878 mil. € |
30,7 min. |
4,3 |
4,0 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku