dátum |
plánovaný
|
odhad NDS
|
stavebné práce
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 71. - 78. | po 2040 | R1 | 42,1 km | 4 | R1 západ | 631 mil. € | 5 713 - 13 545 | 5 | 5 | |||||||
2 | 71. - 78. | po 2040 | R3 | 58,5 km | 2 | R3 juh | Dobrá Niva, Dudince | 611 mil. € | 3 247 - 11 434 | 4 | 4 | ||||||
3 | 71. - 78. | po 2040 | R7 | 71,3 km | 2 | R7 stred | 2 | 553 mil. € | 1 065 - 4 239 | 5 | 5 | ||||||
4 | 71. - 78. | po 2040 | R7 | 32,8 km | 2 | R7 stred | 367 mil. € | 2 228 - 6 331 | 5 | 5 | |||||||
5 | 71. - 78. | po 2040 | R7 | 29,2 km | 2 | R7 stred | 230 mil. € | 2 156 - 6 890 | 5 | 5 | |||||||
6 | 7/2019 | R4 | 4,3 km | 4 | R4 stred | Veľký Šariš | 179 mil. € | 170,0 mil. € | 15 837 - 18 098 | 1 | 3 | ||||||
7 | 8/2019 | R2 | 13,5 km | 4 | R2 stred | 142 mil. € | 161,8 mil. € | 9 007 - 9 998 | 2 | 2 | |||||||
8 | 71. - 78. | po 2040 | R3 | 10,3 km | 2 | R3 stred (Turiec) | 1 | 92 mil. € | 5 098 - 5 557 | 4 | 2 | ||||||
9 | 71. - 78. | po 2040 | D3 | 3,1 km | 4 | D3 Kysuce | 60 mil. € | 5 420 - 8 693 | 5 | 5 | |||||||
10 | 71. - 78. | po 2040 | R5 | 1,7 km | 2 | D3 Kysuce | 54 mil. € | 7 972 | 3 | 4 | |||||||
10 úsekov |
266,8 km |
2 - 4 |
2 919 mil. € |
331,8 mil. € |
1 065 - 18 098 | 3,9 |
4,0 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku