dátum |
plánovaný
|
odhad NDS
|
>12 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||
1 | 25. | 1/2026 | D3 | 10,8 km | 4 | 309 mil. € | 14 176 - 14 186 | 2 105 - 2 649 | 2 | 4 | ||||
2 | 27. | 5/2026 | D3 | 11,2 km | 4 | 410 mil. € | 13 886 - 21 743 | 2 661 - 2 869 | 1 | 1 | ||||
3 | 31. | 11/2026 | D3 | 4,0 km | 4 | 179 mil. € | 15 053 | 2 660 | 1 | 2 | ||||
4 | 41. | 9/2028 | R2 | 11,5 km | 2 | 235 mil. € | 7 793 | 772 | 2 | 4 | ||||
5 | 47. | 7/2029 | R2 | 14,0 km | 2 | 117 mil. € | 5 809 - 8 826 | 593 - 844 | 5 | 4 | ||||
6 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 3 782 - 6 302 | 1 375 - 1 435 | 4 | 3 | ||||
7 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | 90 mil. € | 32 968 | . . . | 5 960 | 5 | 5 | |||
8 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | 107 mil. € | 5 | 5 | ||||||
9 | 71. - 78. | po 2040 | D3 | 3,1 km | 4 | 60 mil. € | 5 420 - 8 693 | 41 - 376 | 5 | 5 | ||||
76,1 km |
2 - 6 |
1 609 mil. € |
3 782 - 32 968 | 3,3 |
3,7 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku