dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
||||||||
1 | 25. | 1/2026 | ![]() | D3 | 10,8 km | 4 | 309 mil. € | 14 176 - 14 186 | 2 | 4 | 1/2029 (+3,0) | |||
2 | 26. | 4/2026 | ![]() | R2 | 20,7 km | 2 | 211 mil. € | 6 969 - 10 726 | 4 | 4 | 4/2028 (+4,8) | |||
3 | 27. | 5/2026 | ![]() | D3 | 11,2 km | 4 | 410 mil. € | 13 886 - 21 743 | 1 | 1 | 5/2029 (+5,1) | |||
4 | 28. - 29. | 8/2026 | ![]() | R4 | 4,0 km | 4 | 105 mil. € | 14 625 | 2 | 2 | 8/2029 (+3,8) | |||
5 | 28. - 29. | 8/2026 | ![]() | R2 | 10,6 km | 2 | 125 mil. € | 6 412 - 8 112 | 4 | 4 | 8/2028 (+5,1) | |||
6 | 30. | 10/2026 | ![]() | R1 | 4,6 km | 4 | 100 mil. € | 11 611 | 4 | 3 | 10/2028 (+3,5) | |||
7 | 31. | 11/2026 | ![]() | D3 | 4,0 km | 4 | 179 mil. € | 15 053 | 1 | 2 | 11/2030 (+6,4) | |||
8 | 32. - 33. | 12/2026 | ![]() | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 6/2033 (+3,3) | ||||
9 | 32. - 33. | 12/2026 | ![]() | R2 | 18,0 km | 2 | 224 mil. € | 10 140 - 11 010 | 3 | 5 | 12/2029 (+2,8) | |||
9 úsekov |
96,3 km |
2 - 4 |
2 435 mil. € |
6 412 - 21 743 | 2,7 |
3,2 |
4/2028 - 6/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku