dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
||||||||
1 | 7/2016 | D4 | 4,4 km | 4 - 6 | 1 | 2 | 11/2021 (+0,4) | |||||||
2 | 7/2016 | D4 | 22,6 km | 4 - 6 | 32 336 - 93 344 | . . . | 1 | 2 | 11/2021 (+0,4) | |||||
3 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 6/2033 (+3,3) | |||||
4 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | 73 mil. € | 5 587 | 5 | 4 | 2/2031 (+4,1) | ||||
5 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | 63 mil. € | 9 492 - 10 279 | 3 | 2 | 11/2030 (+5,2) | ||||
6 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 2/2033 (+4,5) | |||||
7 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 5 814 - 7 518 | 4 | 3 | 5/2033 (+6,1) | ||||
8 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | 129 mil. € | 5 586 - 10 745 | 3 | 2 | 8/2034 (+2,1) | ||||
8 úsekov |
74,7 km |
2 - 6 |
1 303 mil. € |
5 586 - 93 344 | 3,1 |
3,0 |
11/2021 - 8/2034 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku